Notice: Temporary Lane Closures of Taylor Street Estimated to Start on Monday, July 7th, 2025

The upcoming Taylor Street Resurfacing project is estimated to begin on Monday, July 7th, 2025, and have a duration period of 90 days, estimated to be complete on Friday, October 10th, 2025 in which Taylor Street will have temporary lane closures to traffic from Lower Broadway to Water Street intersection. This city-led, DMD championed project is in response to the impact by the Harbor Bridge construction, and the redirection of traffic coming off the bridge from Twigg Street onto Taylor Street.

The project will be conducted in phases that are as follows:

  • Phase 1A (Beginning Monday, July 7, 2025) - Work on west bound traffic lanes on Taylor street between Lower Broadway and Mesquite street with one-way vehicular traffic traveling east bound remaining open
  • Phase 1B - Work on west bound traffic lanes on Taylor street between Mesquite and Chaparral streets with one-way vehicular traffic traveling east bound remaining open
  • Phase 1C - Work on east bound traffic lanes on Taylor street between Lower Broadway and Mesquite street with one-way vehicular traffic traveling west bound remaining open
  • Phase 1D - Work on east bound traffic lanes on Taylor street between Mesquite and Chaparral streets with one-way vehicular traffic traveling west bound remaining open
  • Phase 2A - Work on west bound traffic lanes on Taylor street between Chaparral and Water streets with one-way vehicular traffic traveling east bound remaining open
  • Phase 2B - Work on northeast corner of Taylor and Water streets intersection, with one-way vehicular traffic traveling east bound on Taylor street between Chaparral street and Shoreline boulevard remaining open
  • Phase 2C - Work on east bound traffic lanes on Taylor street between Chaparral and Water streets with one-way vehicular traffic traveling west bound remaining open
  • Phase 2D (Ending Friday, October 10, 2025) - Work on southeast corner of Taylor and Water streets intersection, with one-way vehicular traffic traveling west bound on Taylor street between Chaparral street and Shoreline boulevard remaining open

Work will be deferred on the first Friday of every month (8/1, 9/5, 10/3) to accommodate event footprints and will resume the following Monday. Any updates or changes will be relayed as the information becomes available. For any questions or comments about the Taylor Street Resurfacing project, please contact Daniela Campos, Communications & Public Relations Specialist, at (361)882-2363.